Four Seasons Staff Housing, Dubai, UAE

  • Yapı Tipi:
  • Konut Binaları
Tam Ekran Kapat Sokak Görüntüsü

Built in the heart of an active industrial area of Dubai, the Four Seasons Staff Housing project is a distinguishable building among the surrounding environment. The design’s original time and cost estimates were met by using Peikko's DELTABEAM® solution. 

 Consisting of two parallel buildings with a central connection, the H-shaped structure stands out with floor-to-floor windows built within concrete blocks. The original design featured cast-in-place concrete columns and cast-in-place post-tensioned slabs with external concrete block walls.

The design consists of precast insulated cladding panels, internal precast frames and walls, and Hollow Core Slabs with the following key features:
• Continuous insulation with no thermal breaks
• Flat slabs at cantilevers and corridors
• Fast construction
• Reduced internal finishes

In 2014, the project received Honorable Mention under the Multifamily Housing category at the prestigious PCI Awards. 

www.econstruct.ae

Devamını Oku down-arrow.png

Proje Bilgileri

Proje Boyutu:
21000 m2
Kat Adedi:
5
Yatırımcı:
Bright Start LLC
Yapımcı Firma:
Dubai Contracting Company
Prekast Firması:
e.construct
Teslim Tarihi:
2014
Tamamlanma Tarihi:
2014

Bize Ulaşın

Nirajuthan Selvarajah

Nirajuthan Selvarajah

Project Manager

UAE

[email protected]