Assenheimer Car Park, Heilbronn, Germany

  • Yapı Tipi:
  • Otoparklar
Tam Ekran Kapat

In this project, the conventional construction method of parking decks was converted into a modern and innovative variant with DELTABEAM® and prestressed concrete hollow slabs.

The advantages are a very strongly reduced construction height of the ceilings and thus the entire height of the building. In addition to the need for vertical components such as columns and walls, this saves a considerable amount of cost-intensive facade area.

Due to the lightweight construction in slim-floor construction, outgoing loads up to the foundation could be considerably reduced. The prefabricated construction method with pre-stressed hollow concrete slabs and DELTABEAM® allows a fast construction sequence and thus a safe adherence to the planned construction times.

A further special advantage of the DELTABEAM® construction method is compliance with the R90 fire protection requirement without further measures at the construction site. Especially in the critical ramp area, particularly flat transitions were designed to avoid damage to vehicles. 

Devamını Oku down-arrow.png

Proje Bilgileri

Proje Boyutu:
8000 m2
Kat Adedi:
8
Yapımcı Firma:
WOLFF & MÜLLER Hoch- und Industriebau GmbH & Co. KG
Yapısal Tasarımcı:
GSW Tragwerksplanung GmbH
Prekast Firması:
ELBE delcon Spannbetondecken Vertiebs-GmbH
Teslim Tarihi:
2018
Tamamlanma Tarihi:
2019